3D images
3D Architectural images of the proposed buliding for the site.
Read More3D Architectural images of the proposed buliding for the site.
Read MoreSteel to kitchen floor – concrete pour next week
Read MoreScaffolding and back wall gone, internal stairs all gone. Garage walls up and forming up for ground floor slab.
Read MoreThe rear wall of the main building is starting to be removed, making way for a large steel beam. The Level One floor is down ready for the Bedroom and bathroom. The walls to the garage have started, making way for the formwork for the next slab to start.
Read MoreInternal floors to the main house continued and formwork was prepared to get the ground ready for the concrete pour for the garage slab this morning. The concretors have started polishing the slab, ready for a raw honed finish.
Read MoreExcavation has continued with piers and footings for the slabs being formed and underpinning of the adjacent terrace – not very exciting visually, but needs to be done! The steel beam to the new first floor framing is installed and the existing flooring removed, giving a great mezzanine space for a week or two. Concrete […]
Read MoreThe underpinning, pier digging and excavation for the garage slab has started, not as dramatic as demolition, but progress!
Read MoreNot much of the old house left! The rain didn’t slow anything down luckily, the demolished concrete was taken away and inside the fireplaces, chimneys and a few internal walls were taken down. The site should be clear next week to start forming up the new concrete slabs.
Read MoreAlmost all of the rear section has been demolished – clearing away the rubble takes longer than the demolition!!
Read More