Tathra Paddington

Week 8 – Garage Slab poured!

March 6, 2015No Comments
tathra_paddington_blog_week-8-12

Internal floors to the main house continued and formwork was prepared to get the ground ready for the concrete pour for the garage slab this morning. The concretors have started polishing the slab, ready for a raw honed finish.

Read More

Week 6 – Footings, underpinning and new floors

February 18, 2015No Comments
tathra_paddington_week6_00_week-6-8

Excavation has continued with piers and footings for the slabs being formed and underpinning of the adjacent terrace – not very exciting visually, but needs to be done! The steel beam to the new first floor framing is installed and the existing flooring removed, giving a great mezzanine space for a week or two. Concrete […]

Read More

Week 3 – Demolition continues

January 30, 2015No Comments
tathra_paddington_week3__0000s_0011_tathra_paddington_week3_01

Not much of the old house left! The rain didn’t slow anything down luckily, the demolished concrete was taken away and inside the fireplaces, chimneys and a few internal walls were taken down. The site should be clear next week to start forming up the new concrete slabs.  

Read More